APA Pipeline (May 2015)

APA Pipeline
  • Location: Wallumbilla, QLD
  • Principal Contractor: Energy Works
PROJEM’S SCOPE ‐ Installation of Pipework for APA. This consisted of removal of NRV at four pigging/pig launcher stations between Wallumbilla Compressor Station through to Ballera. This was to allow for Flow Reversal on the main 18” 900lb gas line.
  • Installation of Pup Spools.
  • Flange Management i.e. Bolting.
  • Machine flanges as required.
  • Re-energize pipeline and assist with leak test.